Relevant Information Relevant Information

Relevant Information

March 10

EPM reports the start of the CRW167467 contracting process, whose object is the construction of the final civil works of the Ituango Hydroelectric Project. The estimated date for the submission of bids shall be for June 23, 2022. (See annex)

March 7

Moody’s confirms EPM’s international investment-grade rating and improves outlook to “stable”. (See annex)

March 1

EPM states on information circulating in the media. (See annex)

February 24

EPM reports on the presentation of the list of demands made by the UNIGEEP Trade Union Organization.

February 14

The comissioning of Hidroituango is the best way to mitigate risks, concluded authorities present at the PMU. (See annex)

February 2

EPM informs the public that the Ituango Hydroelectric Project will put into service the first power generation unit on July 26, 2022.

February 1

The Superintendence of Public Services confirmed a sanction to EPM of $1,817,052,000, for the non-entry into commercial operation of the Ituango hydroelectric project in December 2018. EPM is studying the presentation of legal actions.

January 28

EPM informs that it has transmitted the Country Code Survey corresponding to the year 2021, in compliance with external circular 028 of 2014 of the SFC (See annex)

EPM issues opinion on the decision of the Comptroller General of the Republic. (See annex)

EPM reports the technical progress on the fronts of the Ituango Hydroelectric Project (See annex)

January 25

EPM receives a payment from Mapfre Seguros Generales de Colombia S.A. as a result of the Ituango Hydroelectric Project. (See annex)

January 23

ANLA analyzes Pöyry study. (See annex)

January 14

EPM reports the end of the collective dispute with the UNIGEEP trade union organization, in accordance with ruling SL5676-2021, which resolves the appeal for annulment of the Arbitration Award.